The first round of subgrantee selection for the Broadband Equity, Access, and Deployment (BEAD) program in Missouri opens tomorrow, December 5. In preparation for the launch of BEAD Round 1, the Office of Broadband Development (OBD) has published Round 1 grant guidelines interpreting and applying elements of Missouri’s approved Initial Proposal for BEAD funding. Applicants should review these guidelines carefully before submitting applications for BEAD funding.

Key Dates for BEAD Round 1

July 3, 2024 – February 5, 2025
BEAD Pre-Qualification Application 

December 5, 2024 – February 20, 2025
BEAD Scoring Round 1

February 21, 2025 – March 23, 2025
BEAD Scoring Round 1 Sub-round

February 21, 2025 – April 21, 2025
Best and Final Offer (BAFO) Periods

April 22, 2025 (estimated)
Round 1 Determinations

Resources and Assistance

In addition to the grant guidelines, applicants may wish to reference:

Further technical support documents and opportunities for live technical assistance will be offered throughout the application window, beginning with BEAD Round 1 application office hours on Wednesday, December 18, at 3 p.m.

If you have any comments, questions, or concerns, please contact us at broadband@ded.mo.gov or 573-526-1028.

Learn more: https://ded.mo.gov/office-broadband-development/connecting-all-missourians